- Replacing the grinder in wood grinding plant
- Redesign of the predrying group on internal guidence of drying fabrics BM 3
-
Replacement of the approach flow, headbox and wire section of the filler layer BM 2
- Installation of new fans for vacuum system BM 2
- Replacing the winder and redesign of rewinder BM 3
- Replacement of two coating stations BM 3
- Reconstruction of stock preparation PM 3
- Installation of screens and refiners in the stock preparation BM 2 and BM 3
- Installation of thickening drum
- Modernization of preparing starch
- Construction of the biological treatment plant by Sulzer technology
- Construction of anaerobic waste water treatment by Paques technology
- Dosing nutrients infront of anaerobic cleaning
- Waste biogas cogeneration
- Automation of broke line on BM 2 and BM 3
- Setting deburking pland and grinding plant for the production of mechanical pulp
- Ventilation of hall BM 2 and BM 3
- Steam pipeline from TC1 to BM 2
- Installation of Solaronics gas heaters
- Heating of process water with exhaust gas